TCI Construction signed an AIA 201 agreement allowing for a monthly payment to be made as of the 23rd day of each month. The application for the third draw request on the job amounted to 40% completion and was submitted to the architect for review on the 13th of October. How many days before the payment due date is the latest date that the architect shall certify the payment request if the schedule of values accurately reflects the work completed?