Under concrete floor slabs supported directly on the ground, a 6-mil polyethylene vapor retarder with joints lapped not less than ________ shall be placed between the base course or subgrade and the concrete floor slab.
A.
4 inches
B.
6 inches
C.
8 inches
D.
10 inches